760sq.ft. Basement convert to rental unit, view before remodeling process (Before the start of reconstruction)
|
|
|
|
760 sq.ft. Basement view before remodeling process (Before the start of reconstruction, picture-2)
|
|
|
|
Step-1.
Conceptual design (3D computer version, view-1)
|
|
|
|
Conceptual design (3D computer version, view-2)
|
|
|
|
Step-2.
Building Permit drawings. DCRA drawings approval.
|
|
|
|
Step-3.
Concrete slab demolition. Trash removal (Remodeling process, day of 1st).
|
|
|
|
Step-4
Dig up soil. Lowering of floor-level up to 15"(Remodeling process, day of 4st).
|
|
|
|
|
Step-5.
Under-grout plumbing install (Remodeling process, day of 7st).
|
|
|
|
Plumbing install (under-grout plumbing is done). Remodeling process, day of 8st
|
|
|
|
Step-6.
4" Gravel (Remodeling process, day of 10st)
|
|
|
|
Gravel + underground drainage (Remodeling process, day of 12st)
|
|
|
|
Step-7.
Plastic + metal mesh (Remodeling process, day of 13st)
|
|
|
|
Step-8.
Concrete installation (Remodeling process, day of 14st)
|
|
|
|
Concrete slab installed and must be dry for 5-7 days (Remodeling process, day of 15st)
|
|
|
|
|
Concrete slab installed and dried to install frames (Remodeling process, day of 21st)
|
|
|
|
Basement stairway, view from outside (Before the start of reconstruction)
|
|
|
|
Basement stairway, view from inside (Before the start of reconstruction)
|
|
|
|
Step-9.
Destruction of the old stairs. (Remodeling process, day of 23st)
|
|
|
|
Step-10.
New brick stairs is finish. (Remodeling process, day of 30st)
|
|
|
|
New brick stairs is finish. (Remodeling process, day of 30st)
|
|
|
|
Step-11.
Interior frame is done. (Remodeling process, day of 44st)
|
|
|
|
|
Step-12.
Plumbing and electrical rough-in is done. (Remodeling process, day of 52 st)
|
|
|
|
Plumbing and electrical rough-in is done. (Remodeling process, day of 52 st)
|
|
|
|
Step-13.
Installing a sound insulation. (Remodeling process, day of 54 st)
|
|
|
|
Step-14.
Drywall insulation. (Remodeling process, day of 60 st)
|
|
|
|
Drywall insulation. (Remodeling process, day of 60 st)
|
|
|
|
Step-15.
Walls and ceiling finish and paint. (Remodeling process, day of 70 st)
|
|
|
|
Step-16.
Preparation concrete slab for install stain. (Remodeling process, day of 73 st)
|
|
|
|
|
Step-17.
Finished basement for rental unit. Bedroom. (Remodeling process, day of 84 st)
|
|
|
|
Step-17.
Finished basement for rental unit. Bedroom. (Remodeling process, day of 84 st)
|
|
|
|
Step-18.
Finished basement for rental unit. Dining/Living Room. (Remodeling process, day of 87 st)
|
|
|
|
Step-19.
Finished basement for rental unit. Kitchen. (Remodeling process, day of 91 st)
|
|
|
|
Step-20.
Finished basement for rental unit. Bathroom. (Remodeling process, day of 95 st)
|
|
|
|
Step-21.
Finished basement for rental unit. Basement Entry. (Remodeling process, day of 99 st)
|
|
|